News | The ultra-low emission transformation project for flue gas desulfurization and denitrification of Yugang sintering machine, undertaken by Guoshun Group, has officially entered the stage of thermal load commissioning and debugging!

2024-10-26 09:25:49

On October 23, 2024, good news came from Yugang. The Yugang sintering machine flue gas desulfurization and denitrification ultra-low emission renovation project, undertaken by Guoshun Group, completed its acceptance two months ahead of schedule and officially entered the stage of thermal load commissioning and debugging.


At 0:25 on October 24th, the desulfurization system began thermal load testing, and the project officially entered the equipment debugging and operation phase. The project adopts the process route of "circulating fluidized bed desulfurization+SCR denitrification", which will significantly reduce pollutant emissions after operation, and is of great significance for improving the cleanliness level of sintering machines and enhancing regional environmental quality.

Since the start of construction, the Guoshun project team has worked closely with Yugang Company of Jiuquan Iron and Steel Group to overcome the challenges of tight schedule and heavy tasks. By scientifically formulating construction plans, strengthening process control, and making every effort to promote project construction, they completed the handover acceptance two months ahead of schedule, fully demonstrating Guoshun Group's professional strength in the field of environmental protection and winning high recognition from customers. Guoshun Group will continue to adhere to the development strategy of "comprehensive services for industrial environmental protection and energy conservation" in the future, continuously providing customers with high-quality products and services, and achieving sustainable development with customers!

13156357763
gsbgs@sdgs.com.cn